Portal›BOM & Materials›Equipment BOM Binding›212-F-2C/00

Equipment BOM Binding

Actual normalized general-material relationships from SAP BOM source.

RU II Dumai · 6201

212-F-2C/00

5 normalized general-material bindings. Equipment-specific/OEM lines remain in the raw SAP BOM source and family-specific evidence views.

ASSET REGISTER MATCH
SAP MaterialCommodityDescriptionQtyUOMBOM LinesSpare Flag
E230900717FILTER / ELEMENTFILTER ELEMENT,2*69056L06525 IT.5,DWG:2194-PB-211-F2-1C10PCS1-
I090902268BOLT / STUD / NUTBOLT,STUD,A193B7,5/8IN,3.1/2IN,W/2NUT DWG.26071-V2A-H-1-101-00101,REV.05040PCS1-
I090902298BOLT / STUD / NUTBOLT,STUD,A193B7,3/4IN,4.1/4IN,W/2NUT DS.26071-800-MVD-001-0C105,R.1,IT.V28PCS1-
J200750211GASKETGASKET,2",SW,W:SS304,OR,SS316,CL300,RF /-CL300 RF4.5MM5PCS1-
J200750508GASKETGASKET,4",SW,W:SS304,OR,SS316,CL300RF W:SS304 OR SS316CL300RF 4.5MM20PCS1-
A
Maintenance Strategy AssistantLevel 1 · Engineering Question Catalog · Offline · Evidence-grounded
Current context
Portal · BOM & Materials