Portal›Maintenance Plan

Maintenance Plan Engineering

Converts approved task logic into scheduling / trigger rules and lean SAP execution. Not every maintenance activity requires a cyclic work order.

Registered Plans - Assets
36.036
16.0% coverage
Plan Engineering Rows
314
One per maintenance task
SAP Plan Patterns
8
PA-01 through PA-08 plan patterns
Actual Call-Detail Assets
19.574
Matched from RU Sheet2

SAP Plan Patterns

CodePlan PatternUse CaseCall ObjectRoutine Plan?Default GroupingTask Rows
PA-01Monitoring / No Routine SAP PlanContinuous/online monitoring; exception-driven actionNoneNoSystem/area monitoring route37
PA-02Inspection / Routine NotificationSimple inspection / due-date / condition routeNotificationYesRoute/circuit/area/due window120
PA-03Test / Calibration NotificationSimple test/calibration/provingNotificationYesUnit + discipline + method + due window12
PA-04Campaign / Package WORepetitive work needing resources / permit / vendorPackage WOYesArea/unit + discipline/vendor + common window76
PA-05Individual Planned WOUnique asset-specific scheduled workIndividual WOYesEquipment-specific0
PA-06TA / Shutdown PackageIntrusive work requiring outage/TAPackage WOConditionalTA/unit/system/work package14
PA-07Condition-Triggered WORepair/restoration from finding/diagnosticIndividual WONo routine cyclic planFinding/equipment/defect54
PA-08RTF / CorrectiveApproved failure-event workflowCorrective Notification / WONo preventive planEquipment/failure event1
Maintenance Plan Engineering Library - Task ID deep-links back to the Task List.314 rows
Task IDFamilyTask TitleFinal Frequency / Trigger RuleOwnerPlan PatternSAP Plan TypeCall ObjectRoutine?
ST-VESSEL-INS-01Pressure / Process VesselPressure Vessel External Visual InspectionPer approved RBI / applicable code due date; no generic calendar interval.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-VESSEL-INS-02Pressure / Process VesselPressure Vessel Thickness / CML MonitoringPer RBI, corrosion rate, remaining life and CML programme.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-VESSEL-INS-03Pressure / Process VesselPressure Vessel Internal Inspection / NDEPer RBI due date; align with TA only when the approved due window allows.Inspection / Asset IntegrityPA-06 TA / SHUTDOWN PACKAGETA / shutdown due-date control / packagePackage WOConditional
ST-VESSEL-FT-01Pressure / Process VesselPressure Vessel Leak / Pressure Test after Repair or Regulatory TriggerEvent only; no cyclic SAP plan.Reliability + DisciplinePA-07 CONDITION-TRIGGERED WOEvent-triggered workflow; no routine cyclic planIndividual WONo
ST-VESSEL-OVH-01Pressure / Process VesselPressure Vessel Condition-Triggered Repair / RestorationCondition trigger; use TA opportunity where technically justified.Reliability + Maintenance / OEMPA-07 CONDITION-TRIGGERED WOEvent-triggered workflow; no routine cyclic planIndividual WONo
ST-VESSEL-CERT-01Pressure / Process VesselPressure Vessel Statutory Inspection / CertificationPer legal / certification due date. No extension without authorized basis.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-COLUMN-INS-01Process Column / TowerProcess Column External Integrity InspectionPer approved RBI / applicable code due date; no generic calendar interval.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-COLUMN-INS-02Process Column / TowerProcess Column Internal Inspection and Internals AssessmentPer RBI due date; align with TA only when the approved due window allows.Inspection / Asset IntegrityPA-06 TA / SHUTDOWN PACKAGETA / shutdown due-date control / packagePackage WOConditional
ST-COLUMN-CM-01Process Column / TowerProcess Column Process Performance / Fouling SurveillanceContinuous monitoring + monthly engineering review.Reliability / Condition MonitoringPA-01 MONITORING / NO ROUTINE SAP PLANNo routine SAP planNoneNo
ST-COLUMN-OVH-01Process Column / TowerProcess Column Condition-Triggered Internals / Refractory RestorationCondition trigger; use TA opportunity where technically justified.Reliability + Maintenance / OEMPA-06 TA / SHUTDOWN PACKAGETA / shutdown due-date control / packagePackage WOConditional
ST-REACTOR-INS-01Reactor / RegeneratorReactor / Regenerator External Integrity InspectionPer approved RBI / applicable code due date; no generic calendar interval.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-REACTOR-INS-02Reactor / RegeneratorReactor / Regenerator Internal Inspection and Internals AssessmentPer RBI due date; align with TA only when the approved due window allows.Inspection / Asset IntegrityPA-06 TA / SHUTDOWN PACKAGETA / shutdown due-date control / packagePackage WOConditional
ST-REACTOR-CM-01Reactor / RegeneratorReactor / Regenerator Process Performance / Fouling SurveillanceContinuous monitoring + monthly engineering review.Reliability / Condition MonitoringPA-01 MONITORING / NO ROUTINE SAP PLANNo routine SAP planNoneNo
ST-REACTOR-OVH-01Reactor / RegeneratorReactor / Regenerator Condition-Triggered Internals / Refractory RestorationCondition trigger; use TA opportunity where technically justified.Reliability + Maintenance / OEMPA-06 TA / SHUTDOWN PACKAGETA / shutdown due-date control / packagePackage WOConditional
ST-TANK-INS-01Atmospheric / Low-Pressure Storage TankStorage Tank External Integrity InspectionPer applicable code / risk-based due date.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-TANK-INS-02Atmospheric / Low-Pressure Storage TankStorage Tank Thickness / Settlement / Bottom Risk MonitoringPer risk / corrosion-monitoring programme and remaining-life basis.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-TANK-INS-03Atmospheric / Low-Pressure Storage TankStorage Tank Internal InspectionPer code/risk due date; package with TA only within approved due window.Inspection / Asset IntegrityPA-06 TA / SHUTDOWN PACKAGETA / shutdown due-date control / packagePackage WOConditional
ST-TANK-PM-01Atmospheric / Low-Pressure Storage TankStorage Tank Roof Drain / Seal / Breather / Appurtenance Preventive ServiceAnnual formal review + condition-triggered action.Reliability + Maintenance DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
ST-TANK-CERT-01Atmospheric / Low-Pressure Storage TankStorage Tank Statutory / Regulatory InspectionPer legal / certification due date. No extension without authorized basis.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-TANK-CRYO-INS-01Cryogenic / Refrigerated Storage TankCryogenic / Refrigerated Storage Tank External Integrity InspectionPer applicable code / risk-based due date.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-TANK-CRYO-INS-02Cryogenic / Refrigerated Storage TankCryogenic / Refrigerated Storage Tank Thickness / Settlement / Bottom Risk MonitoringPer risk / corrosion-monitoring programme and remaining-life basis.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-TANK-CRYO-INS-03Cryogenic / Refrigerated Storage TankCryogenic / Refrigerated Storage Tank Internal InspectionPer code/risk due date; package with TA only within approved due window.Inspection / Asset IntegrityPA-06 TA / SHUTDOWN PACKAGETA / shutdown due-date control / packagePackage WOConditional
ST-TANK-CRYO-PM-01Cryogenic / Refrigerated Storage TankCryogenic / Refrigerated Storage Tank Roof Drain / Seal / Breather / Appurtenance Preventive ServiceAnnual formal review + condition-triggered action.Reliability + Maintenance DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
ST-TANK-CRYO-CERT-01Cryogenic / Refrigerated Storage TankCryogenic / Refrigerated Storage Tank Statutory / Regulatory InspectionPer legal / certification due date. No extension without authorized basis.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
ST-SPHERE-INS-01Pressure SpherePressure Sphere External / Support Integrity InspectionPer approved RBI / applicable code due date; no generic calendar interval.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
Halaman 1 / 13