Portal›Maintenance Plan
Maintenance Plan Engineering
Converts approved task logic into scheduling / trigger rules and lean SAP execution. Not every maintenance activity requires a cyclic work order.
Registered Plans - Assets
36.036
16.0% coverage
Plan Engineering Rows
314
One per maintenance task
SAP Plan Patterns
8
PA-01 through PA-08 plan patterns
Actual Call-Detail Assets
19.574
Matched from RU Sheet2
SAP Plan Patterns
| Code | Plan Pattern | Use Case | Call Object | Routine Plan? | Default Grouping | Task Rows |
|---|---|---|---|---|---|---|
| PA-01 | Monitoring / No Routine SAP Plan | Continuous/online monitoring; exception-driven action | None | No | System/area monitoring route | 37 |
| PA-02 | Inspection / Routine Notification | Simple inspection / due-date / condition route | Notification | Yes | Route/circuit/area/due window | 120 |
| PA-03 | Test / Calibration Notification | Simple test/calibration/proving | Notification | Yes | Unit + discipline + method + due window | 12 |
| PA-04 | Campaign / Package WO | Repetitive work needing resources / permit / vendor | Package WO | Yes | Area/unit + discipline/vendor + common window | 76 |
| PA-05 | Individual Planned WO | Unique asset-specific scheduled work | Individual WO | Yes | Equipment-specific | 0 |
| PA-06 | TA / Shutdown Package | Intrusive work requiring outage/TA | Package WO | Conditional | TA/unit/system/work package | 14 |
| PA-07 | Condition-Triggered WO | Repair/restoration from finding/diagnostic | Individual WO | No routine cyclic plan | Finding/equipment/defect | 54 |
| PA-08 | RTF / Corrective | Approved failure-event workflow | Corrective Notification / WO | No preventive plan | Equipment/failure event | 1 |
Maintenance Plan Engineering Library - Task ID deep-links back to the Task List.314 rows
| Task ID | Family | Task Title | Final Frequency / Trigger Rule | Owner | Plan Pattern | SAP Plan Type | Call Object | Routine? |
|---|---|---|---|---|---|---|---|---|
| ST-VESSEL-INS-01 | Pressure / Process Vessel | Pressure Vessel External Visual Inspection | Per approved RBI / applicable code due date; no generic calendar interval. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-VESSEL-INS-02 | Pressure / Process Vessel | Pressure Vessel Thickness / CML Monitoring | Per RBI, corrosion rate, remaining life and CML programme. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-VESSEL-INS-03 | Pressure / Process Vessel | Pressure Vessel Internal Inspection / NDE | Per RBI due date; align with TA only when the approved due window allows. | Inspection / Asset Integrity | PA-06 TA / SHUTDOWN PACKAGE | TA / shutdown due-date control / package | Package WO | Conditional |
| ST-VESSEL-FT-01 | Pressure / Process Vessel | Pressure Vessel Leak / Pressure Test after Repair or Regulatory Trigger | Event only; no cyclic SAP plan. | Reliability + Discipline | PA-07 CONDITION-TRIGGERED WO | Event-triggered workflow; no routine cyclic plan | Individual WO | No |
| ST-VESSEL-OVH-01 | Pressure / Process Vessel | Pressure Vessel Condition-Triggered Repair / Restoration | Condition trigger; use TA opportunity where technically justified. | Reliability + Maintenance / OEM | PA-07 CONDITION-TRIGGERED WO | Event-triggered workflow; no routine cyclic plan | Individual WO | No |
| ST-VESSEL-CERT-01 | Pressure / Process Vessel | Pressure Vessel Statutory Inspection / Certification | Per legal / certification due date. No extension without authorized basis. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-COLUMN-INS-01 | Process Column / Tower | Process Column External Integrity Inspection | Per approved RBI / applicable code due date; no generic calendar interval. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-COLUMN-INS-02 | Process Column / Tower | Process Column Internal Inspection and Internals Assessment | Per RBI due date; align with TA only when the approved due window allows. | Inspection / Asset Integrity | PA-06 TA / SHUTDOWN PACKAGE | TA / shutdown due-date control / package | Package WO | Conditional |
| ST-COLUMN-CM-01 | Process Column / Tower | Process Column Process Performance / Fouling Surveillance | Continuous monitoring + monthly engineering review. | Reliability / Condition Monitoring | PA-01 MONITORING / NO ROUTINE SAP PLAN | No routine SAP plan | None | No |
| ST-COLUMN-OVH-01 | Process Column / Tower | Process Column Condition-Triggered Internals / Refractory Restoration | Condition trigger; use TA opportunity where technically justified. | Reliability + Maintenance / OEM | PA-06 TA / SHUTDOWN PACKAGE | TA / shutdown due-date control / package | Package WO | Conditional |
| ST-REACTOR-INS-01 | Reactor / Regenerator | Reactor / Regenerator External Integrity Inspection | Per approved RBI / applicable code due date; no generic calendar interval. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-REACTOR-INS-02 | Reactor / Regenerator | Reactor / Regenerator Internal Inspection and Internals Assessment | Per RBI due date; align with TA only when the approved due window allows. | Inspection / Asset Integrity | PA-06 TA / SHUTDOWN PACKAGE | TA / shutdown due-date control / package | Package WO | Conditional |
| ST-REACTOR-CM-01 | Reactor / Regenerator | Reactor / Regenerator Process Performance / Fouling Surveillance | Continuous monitoring + monthly engineering review. | Reliability / Condition Monitoring | PA-01 MONITORING / NO ROUTINE SAP PLAN | No routine SAP plan | None | No |
| ST-REACTOR-OVH-01 | Reactor / Regenerator | Reactor / Regenerator Condition-Triggered Internals / Refractory Restoration | Condition trigger; use TA opportunity where technically justified. | Reliability + Maintenance / OEM | PA-06 TA / SHUTDOWN PACKAGE | TA / shutdown due-date control / package | Package WO | Conditional |
| ST-TANK-INS-01 | Atmospheric / Low-Pressure Storage Tank | Storage Tank External Integrity Inspection | Per applicable code / risk-based due date. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-TANK-INS-02 | Atmospheric / Low-Pressure Storage Tank | Storage Tank Thickness / Settlement / Bottom Risk Monitoring | Per risk / corrosion-monitoring programme and remaining-life basis. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-TANK-INS-03 | Atmospheric / Low-Pressure Storage Tank | Storage Tank Internal Inspection | Per code/risk due date; package with TA only within approved due window. | Inspection / Asset Integrity | PA-06 TA / SHUTDOWN PACKAGE | TA / shutdown due-date control / package | Package WO | Conditional |
| ST-TANK-PM-01 | Atmospheric / Low-Pressure Storage Tank | Storage Tank Roof Drain / Seal / Breather / Appurtenance Preventive Service | Annual formal review + condition-triggered action. | Reliability + Maintenance Discipline | PA-04 CAMPAIGN / PACKAGE WO | Strategy / single-cycle / counter campaign plan | Package WO | Yes |
| ST-TANK-CERT-01 | Atmospheric / Low-Pressure Storage Tank | Storage Tank Statutory / Regulatory Inspection | Per legal / certification due date. No extension without authorized basis. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-TANK-CRYO-INS-01 | Cryogenic / Refrigerated Storage Tank | Cryogenic / Refrigerated Storage Tank External Integrity Inspection | Per applicable code / risk-based due date. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-TANK-CRYO-INS-02 | Cryogenic / Refrigerated Storage Tank | Cryogenic / Refrigerated Storage Tank Thickness / Settlement / Bottom Risk Monitoring | Per risk / corrosion-monitoring programme and remaining-life basis. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-TANK-CRYO-INS-03 | Cryogenic / Refrigerated Storage Tank | Cryogenic / Refrigerated Storage Tank Internal Inspection | Per code/risk due date; package with TA only within approved due window. | Inspection / Asset Integrity | PA-06 TA / SHUTDOWN PACKAGE | TA / shutdown due-date control / package | Package WO | Conditional |
| ST-TANK-CRYO-PM-01 | Cryogenic / Refrigerated Storage Tank | Cryogenic / Refrigerated Storage Tank Roof Drain / Seal / Breather / Appurtenance Preventive Service | Annual formal review + condition-triggered action. | Reliability + Maintenance Discipline | PA-04 CAMPAIGN / PACKAGE WO | Strategy / single-cycle / counter campaign plan | Package WO | Yes |
| ST-TANK-CRYO-CERT-01 | Cryogenic / Refrigerated Storage Tank | Cryogenic / Refrigerated Storage Tank Statutory / Regulatory Inspection | Per legal / certification due date. No extension without authorized basis. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
| ST-SPHERE-INS-01 | Pressure Sphere | Pressure Sphere External / Support Integrity Inspection | Per approved RBI / applicable code due date; no generic calendar interval. | Inspection / Asset Integrity | PA-02 INSPECTION / ROUTINE NOTIFICATION | Due-date / single-cycle / strategy notification plan | Notification | Yes |
Halaman 1 / 13