SAP Material
C077500096
BUNDLE,TUBE ASSY DWG.AA0953C,REV.2
BOM Relationships
4
Bound Equipment
4
Plant Codes
1
Attribute Completeness
25%
Normalized Candidate
PIPE / TUBE
General MRO / project material
Type: Tube
Not generated — insufficient controlled attributes
Plant Usage
RU V Balikpapan · 6501
4
Actual Equipment Bindings
4 aggregated equipment-material bindings; first 4 displayed.
| Plant / RU | Equipment | Qty | UOM | BOM Lines | Spare Flag |
|---|---|---|---|---|---|
| RU V Balikpapan · 6501 | E-2-02A/00 | 1 | PCS | 1 | - |
| RU V Balikpapan · 6501 | E-2-02B/00 | 1 | PCS | 1 | - |
| RU V Balikpapan · 6501 | E-2-02D/00 | 1 | PCS | 1 | - |
| RU V Balikpapan · 6501 | E-2-02C/00 | 1 | PCS | 1 | - |
Interchangeability is not implied. Reuse across many equipment tags is factual SAP BOM evidence only. Engineering equivalence requires specification and service verification.