SAP Material
H560500200
PIPE,SMLS,SCH40,SRL,CS,A106,GR.B,12"
BOM Relationships
26
Bound Equipment
26
Plant Codes
2
Attribute Completeness
100%
Normalized Candidate
PIPE / TUBE
General MRO / project material
Size: 12IN · Schedule: 40 · Material: ASTM A106 Gr.B/CS · Type: Pipe · Construction: Seamless
PIPE / TUBE|Type=Pipe|Size=12IN|Schedule=40|Material=ASTM A106 Gr.B/CS
Plant Usage
RU III Plaju · 6301
25
RU IV Cilacap · 6401
1
Actual Equipment Bindings
26 aggregated equipment-material bindings; first 26 displayed.
| Plant / RU | Equipment | Qty | UOM | BOM Lines | Spare Flag |
|---|---|---|---|---|---|
| RU III Plaju · 6301 | CD4-3-2/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | CD5-7-5/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-D-002/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-D-004/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-D-006/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-D-005/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-F-004/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-F-005/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-E-012/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-D-003/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-A-005/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-A-010/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-E-011/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | CD2-V-82-001/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-D-011/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | CD3-3-3/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-E-013/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-A-009/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | CD4-1-2/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-A-003/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-A-002/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | CD4-1-1/00 | 2 | JT | 1 | O |
| RU III Plaju · 6301 | CD4-1-3/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | ITP-A-004/00 | 1 | JT | 1 | O |
| RU III Plaju · 6301 | CD5-1-1/00 | 1 | JT | 1 | O |
| RU IV Cilacap · 6401 | GMAT-STA-LOC3/00 | 1 | JT | 1 | - |