SAP Material

I620900133

SHEET,TUBE A1/GM 2143/1/0 REV 0

PIPE / TUBE
BOM Relationships
3
Bound Equipment
3
Plant Codes
1
Attribute Completeness
25%

Normalized Candidate

PIPE / TUBE
General MRO / project material
Type: Tube
Not generated — insufficient controlled attributes

Plant Usage

RU V Balikpapan · 6501
3

Actual Equipment Bindings

3 aggregated equipment-material bindings; first 3 displayed.

Plant / RUEquipmentQtyUOMBOM LinesSpare Flag
RU V Balikpapan · 6501E-3-33A/002PCS1O
RU V Balikpapan · 6501E-3-33C/002PCS1O
RU V Balikpapan · 6501E-3-33B/002PCS1O
Interchangeability is not implied. Reuse across many equipment tags is factual SAP BOM evidence only. Engineering equivalence requires specification and service verification.
A
Maintenance Strategy AssistantLevel 1 · Engineering Question Catalog · Offline · Evidence-grounded
Current context
Portal · BOM & Materials