SAP Material

J200750513

GASKET, SPIRAL WOUND, DIA 12"NB-300 LB B-2356-F402-2A REV 7

GASKET
BOM Relationships
39
Bound Equipment
35
Plant Codes
5
Attribute Completeness
60%

Normalized Candidate

GASKET
General MRO / task material
Size: 12IN · Class: 300 · Type: Spiral Wound
GASKET|Type=Spiral Wound|Size=12IN|Class=300|Material=|Filler=

Plant Usage

RU II Dumai · 6201
21
RU V Balikpapan · 6501
7
RU VI Balongan · 6601
4
RU IV Cilacap · 6401
2
RU III Plaju · 6301
1

Actual Equipment Bindings

35 aggregated equipment-material bindings; first 35 displayed.

Plant / RUEquipmentQtyUOMBOM LinesSpare Flag
RU II Dumai · 6201301-E-6B/001PCS1-
RU II Dumai · 6201301-E-6A/002PCS1-
RU II Dumai · 6201301-R-1/001PCS1-
RU II Dumai · 6201702-V-11/001PCS1-
RU II Dumai · 6201702-V-17/002PCS1-
RU II Dumai · 6201701-V-17/002PCS1-
RU II Dumai · 6201701-V-11/001PCS1-
RU II Dumai · 6201220-V-8/001PCS1-
RU II Dumai · 6201211-V-61B/001PCS1-
RU II Dumai · 6201212-V-104/001PCS1-
RU II Dumai · 6201212-V-61/001PCS1-
RU II Dumai · 6201211-V-31/002PCS1-
RU II Dumai · 6201211-V-61A/001PCS1-
RU II Dumai · 6201212-V-62/001PCS1-
RU II Dumai · 6201211-V-62B/001PCS1-
RU II Dumai · 6201211-V-104/001PCS1-
RU II Dumai · 6201212-V-103/001PCS1-
RU II Dumai · 6201211-V-103/001PCS1-
RU II Dumai · 6201212-V-12/001PCS1-
RU II Dumai · 6201211-V-62A/001PCS1-
RU II Dumai · 6201211-V-12/001PCS1-
RU III Plaju · 6301FD-UPS-02-02/002PCS1-
RU IV Cilacap · 6401LN52MPL8003MS12/001PCS1E
RU IV Cilacap · 6401LN51MPL8001MS12/001PCS1E
RU V Balikpapan · 6501F-4-02/001PCS1R
RU V Balikpapan · 6501E-201-01A/001PCS1R
RU V Balikpapan · 6501O-18/001PCS1R
RU V Balikpapan · 6501O-19/001PCS1R
RU V Balikpapan · 6501E-35-07B/001PCS1R
RU V Balikpapan · 6501E-35-07A/001PCS1R
RU V Balikpapan · 6501D-20-07C/001PCS1R
RU VI Balongan · 660111-E-110B/002PCS1R
RU VI Balongan · 660115-R-104/004PCS2O/R
RU VI Balongan · 660115-F-101/001PCS1O
RU VI Balongan · 660115-V-118/001PCS1-
Interchangeability is not implied. Reuse across many equipment tags is factual SAP BOM evidence only. Engineering equivalence requires specification and service verification.