SECE Assurance & MAH Study Integration
Enterprise-level evidence, reconciliation and governance layer connecting the MAH SECE register to the Maintenance Strategy Portal without altering core maintenance logic.
Keep study evidence authoritative without turning it into an uncontrolled master-data overwrite
The MAH register is preserved as a separate evidence domain. Exact RU + tag matching creates traceable links to equipment; conflicts become governed reconciliation actions.
Study Coverage by RU
Reconciliation Logic
Exact RU + equipment tag match and current portal SECE marker is already present.
Action: Preserve existing core logic; evidence strengthens traceability.
Exact RU + equipment tag match but current portal SECE marker is not set.
Action: Do not auto-write. Raise controlled reconciliation/change request before core marker changes.
MAH study tag/entity has no exact RU + equipment match in the uploaded master.
Action: Classify as equipment, FLOC, line, system/facility barrier element, formatting issue, or genuine master-data gap.
Current portal SECE marker exists, but the equipment is absent from the currently uploaded MAH study register.
Action: Do not demote. Preserve marker until study scope and evidence are reconciled.
SECE Study Register · Unique Tags
Study records are searchable without forcing them into the equipment model.
| RU | Tag | Name (Study) | Node(s) | SECE Element(s) | Status | Linked |
|---|---|---|---|---|---|---|
| RU VII Kasim | 3-VSHH-428A/00 | VIBRATION SWITCH HIGH HIGH CYLINDER CRAN | Node 3 (CRU) | Vibration Intiator | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 3-VSHH-428B/00 | VIBRATION SWITCH HIGH HIGH CYLINDER CRAN | Node 3 (CRU) | Vibration Intiator | MAH Identified · Marker Reconciliation | Yes |
| RU VI Balongan | 4" manual valve on discharge pump | Node 3 (Spherical Tank) | Pipework (Within Plant) | Study Entity · Not Linked to Equipment Master | - | |
| RU VI Balongan | 4" manual valve on spillback line pump | Node 3 (Spherical Tank) | Pipework (Within Plant) | Study Entity · Not Linked to Equipment Master | - | |
| RU VII Kasim | 4-1-P129-A1-H/00 | DISCH 1-P-07A/B TO 1-E-13A INL SHELL | Node 1 (CDU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-1-P130-A1-H/00 | SUCT COMPR 1-K-01 TO FL HDR (BY PASS) | Node 1 (CDU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-1-P131-B1-H/00 | OUTL TUBE 1-E-31 TO INL SHELL 1-E-14C/F | Node 1 (CDU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-1-P132-A1-H/00 | OUT SHELL 1-E-03A/C TO IN SHELL 1-E-02 | Node 1 (CDU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-1-P133-A1-H/00 | OUTLET TUBE SIDE 1-E-01 TO INLET 1-EA-02 | Node 1 (CDU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-1-P133-A1-H/00 (SS) | Node 1 (CDU) | Structural Support | Study Entity · Not Linked to Equipment Master | - | |
| RU VII Kasim | 4-1-P134-A1-H/00 | OUTL SHELL SIDE 1-E-21A TO 5-T-20/21/22 | Node 1 (CDU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-1-P134-A1-H/00 (SS) | Node 1 (CDU) | Structural Support | Study Entity · Not Linked to Equipment Master | - | |
| RU VII Kasim | 4-1-P211-B1-H/00 | LINE FG/PILOT 1-XY-409B1 TO FUR 1-F-01 | Node 1 (CDU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-1-P211-B1-H/00 (SS) | Node 1 (CDU) | Structural Support | Study Entity · Not Linked to Equipment Master | - | |
| RU VII Kasim | 4-1-P212-B1-H/00 | LINE FG/PILOT 1-XY-409B2 TO FUR 1-F-01 | Node 1 (CDU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-1-P212-B1-H/00 (SS) | Node 1 (CDU) | Structural Support | Study Entity · Not Linked to Equipment Master | - | |
| RU VII Kasim | 4-3-H524-B1B-H/00 | DISCH 3-K-01A/B TO 8-3-H-520 (3-EA-02) | Node 3 (CRU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-3-H524A-B1B-H/00 | OUTL DISCH PD 3-PD-02A/04A TO FL HDR | Node 3 (CRU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-3-H524B-B1B-H/00 | OUTL DISCH PD 3-PD-02B/04B TO FL HDR | Node 3 (CRU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-3-H585A-B1B/00 | OUTL SUCT (3-PD-01A)TO INL 3-PSV-176A | Node 3 (CRU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-3-H585B-B1B/00 | OUTLET 3-PD-01B TO INLET 3-PSV-176B | Node 3 (CRU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-3-H586A-B1B/00 | OUTL DISCH (3-PD-02A) TO INL 3-PSV-177 | Node 3 (CRU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-3-H586B-B1B/00 | OUTL DISCH (3-PD-02B) TO INL 3-PSV-177B | Node 3 (CRU) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P415-A1-NI/00 | DISCH 5-P-20A/B TO LN BLNDG&INJKS DYE | Node 4 (OM) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P416-A1-NI/00 | LINE BLNDG&INJEKSI DYE TO 5-T-10/11/12 | Node 4 (OM) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P426-A1-NI/00 | LINE OVERFLOW TANK 5-T-01/25 TO OWS | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P427-A1-NI/00 | OUTL 5-T-26 TO INL 5-T-01/02/25 | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P429-A1-NI/00 | SLOP CDU LINE NO. 4-1-P174 TO 5-T-23/24 | Node 4 (OM) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P430-A1-NI/00 | LINE OVERFLOW TANK 5-T-23 TO OIL KECER | Node 4 (OM) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P431-A1-NI/00 | LINE OVERFLOW TANK 5-T-24 TO OIL KECER | Node 4 (OM) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P432-A1-H/00 | OUTL 1-E-21 TO TANK 5-T-20/21/22 | Node 4 (OM) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P440-A1-NI/00 | LINE OVER FLOW TANK 5-T-20 TO BAK CTRL | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P441-A1-NI/00 | LINE OVER FLOW TANK 5-T-21 TO BAK CTRL | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P442-A1-NI/00 | LINE OVER FLOW TANK 5-T-22 TO BAK CTRL | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P444-A1-NI/00 | OUTLET TANK 5-T-05 TO SUCTION 5-P-25A/B | Node 4 (OM) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P447-A1-NI/00 | OUTLET TANK 5-T-06 TO SUCTION 5-P-16A/B | Node 4 (OM) | Pipework (Within Plant) | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P460-A1-NI/00 | OVERFLOW TANK 5-T-13 TO OWS | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P461-A1-NI/00 | LINE OVERFLOW TANK 5-T-14 TO OWS | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P462-A1-NI/00 | OVERFLOW TANK 5-T-15 TO OWS | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
| RU VII Kasim | 4-5-P466-A1-NI/00 | OVERFLOW TANK 5-T-16 TO OWS | Node 4 (OM) | Overflow line | MAH Identified · Marker Reconciliation | Yes |
Study Node Coverage
| RU | Phase | Node | Study Tag Rows |
|---|---|---|---|
| RU III Plaju | Phase 1 | Node 1 (CD II) | 164 |
| RU III Plaju | Phase 1 | Node 2 (CD III) | 88 |
| RU III Plaju | Phase 1 | Node 3 (CD IV) | 104 |
| RU III Plaju | Phase 2 | Node 04 (CDU V) | 110 |
| RU III Plaju | Phase 2 | Node-05 (STAB C) | 82 |
| RU III Plaju | Phase 2 | Node-07 (Alkylation) | 102 |
| RU III Plaju | Phase 2 | Node-08 (C4 Poly) | 78 |
| RU VI Balongan | Phase 1 | Node 3 (Spherical Tank) | 673 |
| RU VI Balongan | Phase 1 | Node 5 (Intermediate Tank) | 305 |
| RU VI Balongan | Phase 1 | Node 8 (EWTP) | 24 |
| RU VI Balongan | Phase 2 | Node 1 (Jetty) | 61 |
| RU VI Balongan | Phase 2 | Node 2 (SPM&SPL) | 27 |
| RU VI Balongan | Phase 2 | Node 4 (Feed Tanks) | 555 |
| RU VI Balongan | Phase 2 | Node 6 (Product Tanks) | 404 |
| RU VII Kasim | Phase 1 | Node 1 (CDU) | 144 |
| RU VII Kasim | Phase 1 | Node 2 (NHTU) | 19 |
| RU VII Kasim | Phase 2 | Node 3 (CRU) | 42 |
| RU VII Kasim | Phase 2 | Node 4 (OM) | 303 |
| RU VII Kasim | Phase 2 | Node 5-10 (Utility) | 18 |
| TOTAL | 3303 | ||
| Tag Number unik (setelah dedup) | 3236 |
Entity-Resolution Concentration
SECE elements with the highest count of study entities not exact-linked to Equipment Master.
| RU | SECE Element | Study Unique | Linked | Unlinked |
|---|---|---|---|---|
| RU VI Balongan | Pipework (Within Plant) | 396 | 167 | 229 |
| RU VI Balongan | Fixed Fire Water Distribution | 189 | 58 | 131 |
| RU VI Balongan | Flame Detector and Alarm | 129 | 0 | 129 |
| RU VI Balongan | Emergency Alarms (Siren) | 91 | 0 | 91 |
| RU VII Kasim | Structural Support | 55 | 0 | 55 |
| RU VI Balongan | IR Open Path Gas Detector | 52 | 0 | 52 |
| RU VI Balongan | Electrical Motor Control | 64 | 17 | 47 |
| RU VI Balongan | Motor Operated Valve (MOV, EIV) | 211 | 177 | 34 |
| RU VI Balongan | Inert Function | 65 | 33 | 32 |
| RU VI Balongan | Catalytic Point Gas Detector | 83 | 55 | 28 |
| RU VI Balongan | Pressure Safety Valve | 57 | 30 | 27 |
| RU VI Balongan | Cathodic Protection | 19 | 0 | 19 |