Portal›Maintenance Strategy
Maintenance Strategy Library
Corporate Catalog Profile Master. Use filters to move from portfolio profile to the affected equipment population without loading hundreds of rows into one long page.
Catalog Profiles
453
Corporate master
Fully Approved
411
No profile-level action
Profiles Requiring Action
42
Data quality / reclassification / master update
Equipment on Action Profiles
40.982
Close gate before mass build
Catalog Profile Master453 profiles
| Profile | Profile Text | Equipment Family | Final GMS | Equipment | Strategy Ref | Task Package | Core / Cond. | Status | Implementation Gate |
|---|---|---|---|---|---|---|---|---|---|
| 0304 | COLUMN, ABSORBER | Process Column | GMS COLUMN | 58 | STR-0304 | ST-COLUMN | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0305 | COLUMN, SPLITTER | Process Column | GMS COLUMN | 29 | STR-0305 | ST-COLUMN | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0306 | COLUMN, STABILIZER | Process Column | GMS COLUMN | 54 | STR-0306 | ST-COLUMN | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0399 | COLUMN, MISCELLENEOUS | Process Column | GMS COLUMN | 25 | STR-0399 | ST-COLUMN | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0401 | VESSEL, PRESSURE, VERTICAL | Pressure / Process Vessel | GMS VESSEL | 1.800 | STR-0401 | ST-VESSEL | 3/3 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0402 | VESSEL, PRESSURE, HORIZONTAL | Pressure / Process Vessel | GMS VESSEL | 969 | STR-0402 | ST-VESSEL | 3/3 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0403 | VESSEL, NON PRESSURE VERTICAL | Non-Pressure Process Vessel | GMS VESSEL | 212 | STR-0403 | ST-VESSEL-NP | 1/4 | APPROVED – MASTER DATA UPDATE | G2 - MASTER DATA UPDATE BEFORE MASS BUILD |
| 0404 | VESSEL, NON PRESSURE HORIZ. | Non-Pressure Process Vessel | GMS VESSEL | 63 | STR-0404 | ST-VESSEL-NP | 1/4 | APPROVED – MASTER DATA UPDATE | G2 - MASTER DATA UPDATE BEFORE MASS BUILD |
| 0499 | VESSEL, MISCELLENEOUS | Pressure / Process Vessel | GMS VESSEL | 362 | STR-0499 | ST-VESSEL | 3/3 | APPROVED WITH DATA-QUALITY ACTION | G1 - DATA QUALITY ACTION |
| 0501 | BOTTLE, RACK MOUNTED | Pressure Bottle / Receiver | GMS PRESSURE VESSEL | 42 | STR-0501 | ST-VESSEL | 4/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0502 | BOTTLE, INDIVIDUAL | Pressure Bottle / Receiver | GMS PRESSURE VESSEL | 8 | STR-0502 | ST-VESSEL | 4/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0599 | BOTTLE, MISCELLENEOUS | Pressure Bottle / Receiver | GMS PRESSURE VESSEL | 21 | STR-0599 | ST-VESSEL | 4/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0601 | BOILER, WATER TUBE | Boiler | GMS BOILER | 53 | STR-0601 | ST-BOILER | 5/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0602 | BOILER, FIRE TUBE | Boiler | GMS BOILER | 8 | STR-0602 | ST-BOILER | 5/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0603 | BOILER, WASTE HEAT BOILER | Boiler | GMS BOILER | 23 | STR-0603 | ST-BOILER | 5/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0699 | BOILER, MISCELLENEOUS | Boiler | GMS BOILER | 32 | STR-0699 | ST-BOILER | 5/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0701 | FIRE HEATER, CYLINDRICAL TYPE | Fired Heater / Furnace | GMS FURNACE | 84 | STR-0701 | ST-HEATER | 5/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0702 | FIRE HEATER, BOX TYPE | Fired Heater / Furnace | GMS FURNACE | 99 | STR-0702 | ST-HEATER | 5/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0799 | FIRE HEATER, MISCELLENEOUS | Fired Heater / Furnace | GMS FURNACE | 436 | STR-0799 | ST-HEATER | 5/2 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0801 | REACT.®,PACKBED,FXD BED CAT | Reactor / Regenerator | GMS REACTOR & REGENERATOR | 84 | STR-0801 | ST-REACTOR | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0802 | REACT.®,PACKBED,FXD BED NON | Reactor / Regenerator | GMS REACTOR & REGENERATOR | 13 | STR-0802 | ST-REACTOR | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0803 | REACT.®,FLUIDIZEDBED CATAL. | Reactor / Regenerator | GMS REACTOR & REGENERATOR | 15 | STR-0803 | ST-REACTOR | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0804 | REACT.®,FLUIDIZEDBEDNON CAT | Reactor / Regenerator | GMS REACTOR & REGENERATOR | 7 | STR-0804 | ST-REACTOR | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0805 | REACT.®EN.TUB.GASEOUS REAC. | Reactor / Regenerator | GMS REACTOR & REGENERATOR | 1 | STR-0805 | ST-REACTOR | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
| 0899 | REACTOR & REGENERATOR, MISC | Reactor / Regenerator | GMS REACTOR & REGENERATOR | 2 | STR-0899 | ST-REACTOR | 3/1 | APPROVED | G3 - READY FOR TASK / PLAN ENGINEERING |
Halaman 2 / 19