Portal›Maintenance Plan

Maintenance Plan Engineering

Converts approved task logic into scheduling / trigger rules and lean SAP execution. Not every maintenance activity requires a cyclic work order.

Registered Plans - Assets
36.036
16.0% coverage
Plan Engineering Rows
314
One per maintenance task
SAP Plan Patterns
8
PA-01 through PA-08 plan patterns
Actual Call-Detail Assets
19.574
Matched from RU Sheet2

SAP Plan Patterns

CodePlan PatternUse CaseCall ObjectRoutine Plan?Default GroupingTask Rows
PA-01Monitoring / No Routine SAP PlanContinuous/online monitoring; exception-driven actionNoneNoSystem/area monitoring route37
PA-02Inspection / Routine NotificationSimple inspection / due-date / condition routeNotificationYesRoute/circuit/area/due window120
PA-03Test / Calibration NotificationSimple test/calibration/provingNotificationYesUnit + discipline + method + due window12
PA-04Campaign / Package WORepetitive work needing resources / permit / vendorPackage WOYesArea/unit + discipline/vendor + common window76
PA-05Individual Planned WOUnique asset-specific scheduled workIndividual WOYesEquipment-specific0
PA-06TA / Shutdown PackageIntrusive work requiring outage/TAPackage WOConditionalTA/unit/system/work package14
PA-07Condition-Triggered WORepair/restoration from finding/diagnosticIndividual WONo routine cyclic planFinding/equipment/defect54
PA-08RTF / CorrectiveApproved failure-event workflowCorrective Notification / WONo preventive planEquipment/failure event1
Maintenance Plan Engineering Library - Task ID deep-links back to the Task List.314 rows
Task IDFamilyTask TitleFinal Frequency / Trigger RuleOwnerPlan PatternSAP Plan TypeCall ObjectRoutine?
EL-MOTOR-FT-01Electric MotorElectric Motor Functional / Protection TestAt approved test due date; use outage window if isolation/shutdown is required.Reliability + DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-MOTOR-OVH-01Electric MotorElectric Motor Condition-Triggered Repair / OverhaulCondition trigger; execute in next suitable outage unless risk requires earlier action.Reliability + Maintenance / OEMPA-07 CONDITION-TRIGGERED WOEvent-triggered workflow; no routine cyclic planIndividual WONo
EL-TRANSFORMER-INS-01TransformerTransformer Visual / Physical Condition InspectionPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-TRANSFORMER-CM-01TransformerTransformer Thermography / Electrical Condition MonitoringPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Reliability / Condition MonitoringPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-TRANSFORMER-PM-01TransformerTransformer Detailed Preventive Maintenance / Cleaning / Torque CheckPer OEM requirement and planned outage window.Reliability + Maintenance DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-TRANSFORMER-FT-01TransformerTransformer Functional / Protection TestAt approved test due date; use outage window if isolation/shutdown is required.Reliability + DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-TRANSFORMER-OVH-01TransformerTransformer Condition-Triggered Repair / OverhaulCondition trigger; execute in next suitable outage unless risk requires earlier action.Reliability + Maintenance / OEMPA-07 CONDITION-TRIGGERED WOEvent-triggered workflow; no routine cyclic planIndividual WONo
EL-SWGR-MCC-INS-01Switchgear / MCCSwitchgear / MCC Visual / Physical Condition InspectionPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-SWGR-MCC-CM-01Switchgear / MCCSwitchgear / MCC Thermography / Electrical Condition MonitoringPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Reliability / Condition MonitoringPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-SWGR-MCC-PM-01Switchgear / MCCSwitchgear / MCC Detailed Preventive Maintenance / Cleaning / Torque CheckPer OEM requirement and planned outage window.Reliability + Maintenance DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-SWGR-MCC-FT-01Switchgear / MCCSwitchgear / MCC Functional / Protection TestAt approved test due date; use outage window if isolation/shutdown is required.Reliability + DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-SWGR-MCC-OVH-01Switchgear / MCCSwitchgear / MCC Condition-Triggered Repair / OverhaulCondition trigger; execute in next suitable outage unless risk requires earlier action.Reliability + Maintenance / OEMPA-07 CONDITION-TRIGGERED WOEvent-triggered workflow; no routine cyclic planIndividual WONo
EL-GENERATOR-INS-01Generator / Excitation / Generator ControlGenerator / Excitation Visual / Physical Condition InspectionPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-GENERATOR-CM-01Generator / Excitation / Generator ControlGenerator / Excitation Thermography / Electrical Condition MonitoringPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Reliability / Condition MonitoringPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-GENERATOR-PM-01Generator / Excitation / Generator ControlGenerator / Excitation Detailed Preventive Maintenance / Cleaning / Torque CheckPer OEM requirement and planned outage window.Reliability + Maintenance DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-GENERATOR-FT-01Generator / Excitation / Generator ControlGenerator / Excitation Functional / Protection TestAt approved test due date; use outage window if isolation/shutdown is required.Reliability + DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-GENERATOR-OVH-01Generator / Excitation / Generator ControlGenerator / Excitation Condition-Triggered Repair / OverhaulCondition trigger; execute in next suitable outage unless risk requires earlier action.Reliability + Maintenance / OEMPA-07 CONDITION-TRIGGERED WOEvent-triggered workflow; no routine cyclic planIndividual WONo
EL-UPS-DC-INS-01UPS / DC Power / Battery ChargerUPS / DC Power / Battery Charger Visual / Physical Condition InspectionPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-UPS-DC-CM-01UPS / DC Power / Battery ChargerUPS / DC Power / Battery Charger Thermography / Electrical Condition MonitoringPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Reliability / Condition MonitoringPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-UPS-DC-PM-01UPS / DC Power / Battery ChargerUPS / DC Power / Battery Charger Detailed Preventive Maintenance / Cleaning / Torque CheckPer OEM requirement and planned outage window.Reliability + Maintenance DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-UPS-DC-FT-01UPS / DC Power / Battery ChargerUPS / DC Power / Battery Charger Functional / Protection TestAt approved test due date; use outage window if isolation/shutdown is required.Reliability + DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes
EL-UPS-DC-OVH-01UPS / DC Power / Battery ChargerUPS / DC Power / Battery Charger Condition-Triggered Repair / OverhaulCondition trigger; execute in next suitable outage unless risk requires earlier action.Reliability + Maintenance / OEMPA-07 CONDITION-TRIGGERED WOEvent-triggered workflow; no routine cyclic planIndividual WONo
EL-PANEL-INS-01Electrical Panel / Distribution / Control PanelElectrical Panel Visual / Physical Condition InspectionPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Inspection / Asset IntegrityPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-PANEL-CM-01Electrical Panel / Distribution / Control PanelElectrical Panel Thermography / Electrical Condition MonitoringPeriodic baseline from OEM/site history/P-F interval; adverse condition triggers earlier action.Reliability / Condition MonitoringPA-02 INSPECTION / ROUTINE NOTIFICATIONDue-date / single-cycle / strategy notification planNotificationYes
EL-PANEL-PM-01Electrical Panel / Distribution / Control PanelElectrical Panel Detailed Preventive Maintenance / Cleaning / Torque CheckPer OEM requirement and planned outage window.Reliability + Maintenance DisciplinePA-04 CAMPAIGN / PACKAGE WOStrategy / single-cycle / counter campaign planPackage WOYes